Case Studies

MOV Emergency Distribution Board – North Sea Asset


Electon was contracted to resolve an issue on a North Sea asset where a number of MOV’s (Motor Operated Valves) were required to be operated during asset black start to allow the run up of the main generation. No existing Emergency MOV distribution board was installed on the asset. Electon designed and specified a new 3 Phase distribution board and sourced an existing power supply from an emergency switchboard to supply power to it, whilst carrying out all engineering design to ensure compliance with national, international and client standards. Thereby giving the asset the ability to run the MOV’s during black start and resolving the clients issues with the run up of the main generation. We also provided engineering input into the completion of design drawings and the procurement of the equipment for the work scope.

 

Smart Mix Metering Skid – Oil and Gas Operator in the North Sea


A new metering skid was being installed on a North Sea asset. Electon provided electrical engineering design input and commissioning support to set up the VFD’s to run on the vendor control system. This involved liaison with the clients 3rd party contractors to understand the requirements and develop a solution.

 

Calorifier Control Panel – North Sea Asset


A calorifier control panel was required to run a colorifier heater at certain time intervals to meet HSE legislation on legionella in standing water. Electon designed and specified the control panel and sub contracting the scope to a local panel builder. The project was delivered on time to meet a tight shutdown schedule.

 

Temporary Generator – North Sea Asset


A temporary generator was to be installed on one of our clients North Sea assets. Electon carried out all electrical engineering input and vendor liaison. This included a Load Study, numerous Calculations, Protection Settings Schedule, Asset Liaison, Vendor Liaison, Attendance at FAT and Work Pack Input. Along with engineering input into the Single Line Diagram, Cable Schedule, Termination Diagram and Materials Requisition. The project was completed on time and was a complete success. Our client fed back that they were particularly pleased with the professional level of support they received on the project.